7 Sep 2019 Work Day report

Trip report Carroll work day September 7, 2019 Participants (riding with Rick) Rick Hines Jim Cooley* Julie Swetnam* Shannon Robinson* Jay Kennedy* Nick Kennedy* Jamie Euliss Rita Worden Martin Carmichael Jeff Page Randy Bruegger Greg Fry Summary: We finished...

2 April 2019 – Work day

After a rough start we finally concluded a productive work day and I can check two items off our “to do list”. Bill Gee and a newcomer to the CCC, Shannon Robinson, arrived about 15 minutes before our planned 7:00 AM departure (Bill’s always early). While packing...

Surface work March 10, 2019

Bernhard Arnold, Jeff Page, and Rick Hines departed Rick’s home in his truck Sunday morning for a long delayed work day at Carroll. We picked up electrical wire at Menards before hitting the highway. Our next stop was at Randy Bruegger’s home near Warsaw to load...

9 Feb 2019 Surface work day

Carroll Cave Surface Work Report 2/9/2019 I got to the Schoolhouse around 6pm on Friday evening. I was surprised to see the schoolhouse area was tore up from some bulldozer work. A new gate leads into the schoolhouse area. I pulled the camper in, having to slip into...

We got the shaft!

From Rick Hines, president of the Carroll Cave Conservancy: On December 28, 2018, the Carroll Cave Conservancy became the owner of six acres of land around the back door entrance, a 40-foot easement from the back door entrance to the road, and cave rights under 479...